Hunter Water introduces new environmental assessment process

  1. Complying Development: A CDC issued by registered subdivision certifiers can be accepted for Hunter Water projects. Once the CDC has been issued by the certifier, it can be submitted to Hunter Water with the design drawings and Application for Recognition of Complying Development form.
  2. Council Consent: Hunter Water recognises development consent issued by Council including water and/or sewer design. For this pathway, Hunter Water requires an Application for Recognition of Council Consent, a copy of the development consent, stamped plans, and Statement of Environmental Effects.
  3. Other Authority Approvals: Hunter Water recognises approvals issued by other authorities that cover the scope of the proposed water and/or sewer works. For this pathway, Hunter Water requires an Application for Recognition of Other Authority Approval form, a copy of the approval, and environmental assessment that was approved by the other authority.
  4. Review of Environmental Factors: For works that aren’t covered by the other pathways, Hunter Water requires a REF in the revised template. The REF can be submitted to Hunter Water with an Application for Review of Environmental Factors form and a copy of the detailed design drawings. Hunter Water will issue an Instrument of Approval including requirements for the construction and operation of the activity, if the REF sufficiently describes the works undertaken, identifies environmental risks and proposes how the risks will be managed.

How do you make a submission?

The required forms and attachments can be submitted by the Accredited Design Consultant to Hunter Water by emailing design_submission@hunterwater.com.au

Payment for the REF assessment fee is required once the REF has been submitted, and the first review of the REF report is generally completed within 30 to 60 days following receipt of payment. Additional reviews are usually completed within 30 days and any further reviews beyond the second review will include an additional assessment fee.  

How can BRS assist?

We are Accredited Hunter Water Design Consultants and are experienced in a variety of minor and major water and sewer infrastructure works projects for developers, Hunter Water, and local government authorities.

With the changes to Hunter Water’s environmental assessment process, we can assist you throughout the process by providing civil design, town planning, project management and certification services including:

  • Issuing Complying Development Certificates as a Registered Certifier.
  • Providing project management services to help streamline the project application process through Hunter Water’s Property Self Service Portal and ensure the correct documentation is included within the relevant Environmental Assessment pathway.
  • Preparing concept and final water and sewage reticulation designs and certifying the drawings.
  • Preparing Environmental Impact Assessments (EIA), Statement of Environmental Effects (SoEE), Review of Environmental Factors (REF).
  • Engaging early in the DA, CDC, Public Authority approvals process to determine the most beneficial environmental assessment approval pathway for your project and streamlining the submission of documentation to Hunter Water.

If you have any questions about the environmental approval process or how we can assist with your next development, please don’t hesitate to contact us.

The new process allows applicants to choose one of four environmental approval pathways:

  1. Complying development certificates: Hunter Water will accept complying development certificates (CDC) from private certifiers for simple works that are deemed low risk.
  2. Part 4 council consent: Hunter Water will accept Part 4 council consent where water and/or sewer design drawings are included in the development application.
  3. Part 5 approvals: Hunter Water will accept Part 5 approvals from other authorities where the water and/or sewer proposal has been included in the scope of the approval.
  4. Hunter Water Review of Environmental Factors: Hunter Water will continue to accept Review of Environmental Factors (REF), however, the REF will need to be prepared in the revised REF template provided by Hunter Water to help streamline the process.

What documentation is required?

Hunter Water requires an Environmental Assessment Application Form for all applications, allowing applicants to nominate the environmental assessment pathway for the proposal. The design consultant is required to complete the form and submit it to Hunter Water.

The documentation required for each environmental approval pathway includes:

  1. Complying Development: A CDC issued by registered subdivision certifiers can be accepted for Hunter Water projects. Once the CDC has been issued by the certifier, it can be submitted to Hunter Water with the design drawings and Application for Recognition of Complying Development form.
  2. Council Consent: Hunter Water recognises development consent issued by Council including water and/or sewer design. For this pathway, Hunter Water requires an Application for Recognition of Council Consent, a copy of the development consent, stamped plans, and Statement of Environmental Effects.
  3. Other Authority Approvals: Hunter Water recognises approvals issued by other authorities that cover the scope of the proposed water and/or sewer works. For this pathway, Hunter Water requires an Application for Recognition of Other Authority Approval form, a copy of the approval, and environmental assessment that was approved by the other authority.
  4. Review of Environmental Factors: For works that aren’t covered by the other pathways, Hunter Water requires a REF in the revised template. The REF can be submitted to Hunter Water with an Application for Review of Environmental Factors form and a copy of the detailed design drawings. Hunter Water will issue an Instrument of Approval including requirements for the construction and operation of the activity, if the REF sufficiently describes the works undertaken, identifies environmental risks and proposes how the risks will be managed.

How do you make a submission?

The required forms and attachments can be submitted by the Accredited Design Consultant to Hunter Water by emailing design_submission@hunterwater.com.au

Payment for the REF assessment fee is required once the REF has been submitted, and the first review of the REF report is generally completed within 30 to 60 days following receipt of payment. Additional reviews are usually completed within 30 days and any further reviews beyond the second review will include an additional assessment fee.  

How can BRS assist?

We are Accredited Hunter Water Design Consultants and are experienced in a variety of minor and major water and sewer infrastructure works projects for developers, Hunter Water, and local government authorities.

With the changes to Hunter Water’s environmental assessment process, we can assist you throughout the process by providing civil design, town planning, project management and certification services including:

  • Issuing Complying Development Certificates as a Registered Certifier.
  • Providing project management services to help streamline the project application process through Hunter Water’s Property Self Service Portal and ensure the correct documentation is included within the relevant Environmental Assessment pathway.
  • Preparing concept and final water and sewage reticulation designs and certifying the drawings.
  • Preparing Environmental Impact Assessments (EIA), Statement of Environmental Effects (SoEE), Review of Environmental Factors (REF).
  • Engaging early in the DA, CDC, Public Authority approvals process to determine the most beneficial environmental assessment approval pathway for your project and streamlining the submission of documentation to Hunter Water.

If you have any questions about the environmental approval process or how we can assist with your next development, please don’t hesitate to contact us.

The purpose of Hunter Water’s environmental assessment process is to consider how proposed water and sewer works may impact the environment and the local community and to ensure any impacts are addressed during the application and approvals process.

The new process allows applicants to choose a broader range of approval pathways for their development and infrastructure projects. The process commenced in August 2024, with a transition period for any existing works in progress until the end of 2024.

How does the environmental assessment process work?

The new process allows applicants to choose one of four environmental approval pathways:

  1. Complying development certificates: Hunter Water will accept complying development certificates (CDC) from private certifiers for simple works that are deemed low risk.
  2. Part 4 council consent: Hunter Water will accept Part 4 council consent where water and/or sewer design drawings are included in the development application.
  3. Part 5 approvals: Hunter Water will accept Part 5 approvals from other authorities where the water and/or sewer proposal has been included in the scope of the approval.
  4. Hunter Water Review of Environmental Factors: Hunter Water will continue to accept Review of Environmental Factors (REF), however, the REF will need to be prepared in the revised REF template provided by Hunter Water to help streamline the process.

What documentation is required?

Hunter Water requires an Environmental Assessment Application Form for all applications, allowing applicants to nominate the environmental assessment pathway for the proposal. The design consultant is required to complete the form and submit it to Hunter Water.

The documentation required for each environmental approval pathway includes:

  1. Complying Development: A CDC issued by registered subdivision certifiers can be accepted for Hunter Water projects. Once the CDC has been issued by the certifier, it can be submitted to Hunter Water with the design drawings and Application for Recognition of Complying Development form.
  2. Council Consent: Hunter Water recognises development consent issued by Council including water and/or sewer design. For this pathway, Hunter Water requires an Application for Recognition of Council Consent, a copy of the development consent, stamped plans, and Statement of Environmental Effects.
  3. Other Authority Approvals: Hunter Water recognises approvals issued by other authorities that cover the scope of the proposed water and/or sewer works. For this pathway, Hunter Water requires an Application for Recognition of Other Authority Approval form, a copy of the approval, and environmental assessment that was approved by the other authority.
  4. Review of Environmental Factors: For works that aren’t covered by the other pathways, Hunter Water requires a REF in the revised template. The REF can be submitted to Hunter Water with an Application for Review of Environmental Factors form and a copy of the detailed design drawings. Hunter Water will issue an Instrument of Approval including requirements for the construction and operation of the activity, if the REF sufficiently describes the works undertaken, identifies environmental risks and proposes how the risks will be managed.

How do you make a submission?

The required forms and attachments can be submitted by the Accredited Design Consultant to Hunter Water by emailing design_submission@hunterwater.com.au

Payment for the REF assessment fee is required once the REF has been submitted, and the first review of the REF report is generally completed within 30 to 60 days following receipt of payment. Additional reviews are usually completed within 30 days and any further reviews beyond the second review will include an additional assessment fee.  

How can BRS assist?

We are Accredited Hunter Water Design Consultants and are experienced in a variety of minor and major water and sewer infrastructure works projects for developers, Hunter Water, and local government authorities.

With the changes to Hunter Water’s environmental assessment process, we can assist you throughout the process by providing civil design, town planning, project management and certification services including:

  • Issuing Complying Development Certificates as a Registered Certifier.
  • Providing project management services to help streamline the project application process through Hunter Water’s Property Self Service Portal and ensure the correct documentation is included within the relevant Environmental Assessment pathway.
  • Preparing concept and final water and sewage reticulation designs and certifying the drawings.
  • Preparing Environmental Impact Assessments (EIA), Statement of Environmental Effects (SoEE), Review of Environmental Factors (REF).
  • Engaging early in the DA, CDC, Public Authority approvals process to determine the most beneficial environmental assessment approval pathway for your project and streamlining the submission of documentation to Hunter Water.

If you have any questions about the environmental approval process or how we can assist with your next development, please don’t hesitate to contact us.

BRS’ new office locations: A strategic move for future growth

Interior view of an office space

As part of our strategic vision for BRS’s growth, we identified the need to optimise our current office spaces while also expanding into new locations.

In 2024, we have refreshed our Sydney office and relocated our Central Coast, Hunter, Coffs Harbour and North Queensland offices into larger spaces, enhancing our ability to serve clients and creating a better environment for our team.

BRS’s CEO and Director, Andrea McDonald said, ‚ÄúOur offices have been designed with our team and clients in mind, ensuring a welcoming and functional workspace for all. With modern amenities and technology, our new offices are prepared to support our continued growth.‚Äù

All of our office refurbishments and relocations were undertaken with our team’s wellbeing front of mind, to ensure we continue providing flexible, collaborative, and conveniently located spaces for our team to work and socialise.

Office Refurbishments and Relocations

Sydney Office, Dharug Country

We kicked off by refurbishing our existing Sydney office in Norwest, where we have been located since our establishment almost 15 years ago.

To help optimise the functionality of the existing space, our Sydney office was refitted to accommodate more desk spaces and new flexible and collaborative meeting areas. The fitout has helped to increase the capacity in our Sydney office by 30%, ensuring we are well-positioned as our team continues to grow.

Central Coast Office, Darkinjung Country

Our Central Coast office has moved to Erina, an ideal location in the heart of the Central Coast providing optimal accessibility and opportunity for clients and team members alike.

This strategic relocation ensures our team is well-positioned to actively support the planned growth and revitalisation of the Central Coast region in the coming years.

Pictured: Our Sydney and Central Coast offices.

Hunter Office, Awabakal and Worimi Country

Our new Hunter office is strategically positioned in Broadmeadow, allowing our experienced team to assist with the planned urban renewal and growth in the area over the years to come.

The relocation and fitout of our new Hunter office space has been an intentional process to create an environment that fosters collaboration and productivity.

Coffs Harbour Office, Gumbaynggirr Country

Our Coffs Harbour office has moved into a brand new suite with modern facilities, conveniently located near Coffs Harbour’s key landmarks.

The positioning of our Coffs Harbour office allows us to assist with the exciting opportunities for growth in the region, including providing certification services from the Mid-North Coast to the Queensland border.

North Queensland Office, Bindal and Wulgurukaba Country

Strategically located in Townsville, our North Queensland office allows us to better service our clients in Queensland and ensure we are well-positioned to assist with upcoming opportunities in the thriving region.

Looking ahead: Welcoming clients and partners to our new spaces

As we settle into our new and refreshed office spaces, we invite our team, clients and partners to join us in this exciting new chapter. Our doors are always open, and we look forward to collaborating with you on your next project and continuing to work together to create better outcomes for our local communities.

Our new office addresses are:

  • Sydney: Suite 603, 12 Century Circuit, Baulkham Hills
  • Central Coast: Suite 1, T2/34, Karalta Road, Erina
  • Hunter: 1/22 Newton Street, Broadmeadow
  • Coffs Harbour: 1/3 Ted Ovens Drive, Coffs Harbour
  • Townsville: 13-15 Allen Street, South Townsville

If you have any questions about how we can assist with any upcoming projects, please don’t hesitate to get in touch.